Practice Question: Critical Path Duration Based on Revised Schedule

NCEES Civil PE Specification Project Planning: Activity identification and sequencing


Problem

You are working on a construction project and are reviewing the following schedule network diagram produced by your intern.  Upon reviewing the diagram, you notice activity A should actually be one day in duration.


What is the project duration based on the critical path?
 

Select an Answer: